WSDOT SR167 Bridge Replacement Project Update



The preconstruction meeting for the Washington State Department of Transportation (WSDOT) SR167 bridge replacement project took place on Thursday, April 17th. Construction is scheduled to commence on May 1st and is broken into three stages:

· Stage one will include the relocation of the steel truss bridge to the east, to be used as the detour route, while the new bridge is being built. Stage one is scheduled to run from May 1st through August 1st, with the bridge scheduled to be moved at the end of July.

· Stage two - construction of the new bridge - will take place August 1st through July 1st.

· Stage three will include elimination of the detour alignment and removal of the old steel bridge to the unused WSDOT SR17 right-of-way for storage.

Signage will be installed directing those who have questions and/or concerns to a 1-800 number or the WSDOT project specific web site.